Start with the rooms, not the catalogue
A whole-house interior is a sequence of decisions: layout, joinery, finishes, lighting and furniture. Begin with floor plans and a room-by-room list of what you want to keep, change or add. Reference images help, but dimensions and priorities are what make a quotation usable.
Turn plans into a room schedule
For each room, record the joinery (kitchen, wardrobes, vanities, doors, wall panels), the surfaces (stone, tiles, flooring, paint) and the fittings (lighting, hardware, bathroom). This becomes the specification we price and manufacture against.
Approve samples before production
Stone slabs, timber veneers, door finishes, edge profiles and hardware should be approved physically or on video. Shop drawings then fix dimensions, openings and interfaces before any board is cut.
Plan production and delivery together
Custom joinery normally takes 45–75 days after approvals. Tiles, stone and bathroom items are ordered in parallel, checked at our Foshan warehouse and packed into a planned container load. Share your site programme early so delivery and installation sequencing match.
Prepare the site for installation
Confirm wall and floor levels, electrical and plumbing positions, and access for large pieces. We provide installation drawings and remote support; in selected markets, WAYLAND can arrange site teams.